Tour Montparnasse: renovation scaled back, €400M
Co-owners of the Tour Montparnasse: a less ambitious roadmap, a target budget of €400 million, but an unclear building permit.
The essentials
- The co-owners of the Tour Montparnasse have approved the main principles of a renovation project considerably less ambitious than the previous one.
- The target budget is €400 million, compared with €800 million for the plan abandoned in September.
- The 2019 building permit could remain valid until 8 April 2027, without written confirmation from the Paris City Hall.
- Two scenarios are under discussion, each carrying risks of delay or legal uncertainty.
A first project shelved after internal disputes
According to BFM Immo, the major renovation project for the Tour Montparnasse, Paris's tallest skyscraper, will not go ahead as planned. It had been abandoned in September following tensions between co-owners, notably companies and investors, who gathered a large majority against launching the first phase of works.
The main sticking point concerned the exchange of square metres between co-owners. It was this that caused the first plan to fail, and it remains an obstacle going forward.
A more sober roadmap
At a vote, the co-owners approved a roadmap by a large majority, 84% of votes according to several participants. The new project should favour a sober and economical approach: no major restructuring, no extension, no hotel.
The stated aim is to renovate by 2031 the façades, technical equipment and common areas, to create shops and services open to the public on the lower floors, and to lay out a greener forecourt. The whole project must comply with Paris's bioclimatic local urban plan and aim for a low-carbon commitment.
The idea of an agricultural greenhouse on the roof and of widening the base of the tower has been dropped, in order to remain within a budget considered reasonable.
A disputed estimate
The target budget of €400 million does not include agency fees or construction risks, and will need to be specified as the project progresses, the chair of the co-ownership board said. Frédéric Lemos, former chair of the co-ownership board, disputes this figure and estimates that it would reach €760 million once all costs are accounted for.
Uncertainty over the building permit
The permit obtained in 2019 had been extended until 26 November 2026. Given the appeals lodged, it would ultimately be valid until 8 April 2027, a date not confirmed in writing by the Paris City Hall. The City is, however, reported to have expressed its wish for the permit to be implemented.
Two scenarios were presented without a vote. Scenario A involves applying for a new permit and abandoning the existing one, at the risk of lengthy delays due to appeals. Scenario B launches asbestos removal works before April 2027 in order to use the existing permit, before an amended permit is filed, but its success depends on the works being started in time. The supervisory board considers Scenario A the one to favour in order to move forward more quickly. The assembly also voted to launch a tender to appoint the company responsible for the stripping-out and asbestos removal.
What this means for Cannes and the Côte d'Azur
What this means for Cannes and the Côte d'Azur: this case concerns a Parisian co-ownership, but it illustrates a useful point for any owner, seller or buyer in the region: a co-ownership works project depends heavily on agreement between co-owners, on the validity of permits and on any possible appeals, which can delay a site by several years. Before buying a property in co-ownership or launching works, it is wise to review the minutes of the general meetings, the multi-year works plan and the authorisations in progress, and to seek advice from a notary or a co-ownership professional.
Article written by agwelcome with the help of artificial intelligence, based on the BFM Immo article cited at the top of the page. It does not replace the advice of a notary, lawyer or other professional. Topics: Property market.