News ·

Nice: L'Avant-Scène finally restarts its site after 4 years

The developer Quartus plans to restart the Avant-Scène construction site in Nice in December, after four years of legal deadlock with the insurer.

The essentials

  • The Avant-Scène construction site in Nice has been halted since May 2022 after part of the building sank.
  • The developer Quartus announces that work will resume in December, following the appointment of a new insurer.
  • Consolidation works are estimated to take 36 months, with expected delivery in the third quarter of 2029.
  • Some 600 buyers must wait well beyond the originally scheduled delivery date of late 2023.

A site frozen since May 2022

According to Nice-Matin, the L'Avant-Scène development in the Grand Arenas district has made no progress since 2022. That year, the east wing of the building sank by 16 centimetres into the alluvial soils of the Var riverbed. The whole project, which covers 36,000 square metres, was then brought to a halt.

The off-plan buyers, who number around 600, were expecting an apartment, a student room or a unit in the future senior residence. Their timetable slipped by several years without the site restarting.

A legal tug-of-war with the insurer

A court-appointed expert has identified a technical solution to restore the building to level. Its implementation was, however, delayed by a dispute with the insurer, which was reluctant to fund a repair whose durability it doubted. It even proposed partial demolition followed by reconstruction.

The City of Nice has stated that it would not issue new planning permissions in this case. Ultimately, the developer obtained a court-ordered guarantee of the €56 million in financing needed to complete the scheme, which made this option unnecessary.

A restart under supervision

According to the letter sent by Quartus to its buyers and dated 30 September 2026, a new insurer has been found. According to the developer, this step clears the last essential prerequisite for the repair works.

The new insurer has, however, set a condition: the works must be carried out under the supervision of its own technical expert. The foundations must be reinforced with dozens of micropiles reaching down to 40 metres, which is far from a minor repair.

Still long delays for buyers

The developer now expects delivery in the third quarter of 2029, whereas the originally scheduled date was the end of 2023. For buyers, the resumption is good news, but it does not significantly shorten the wait.

The buyers concerned would be well advised to follow exchanges with the developer and to read their off-plan sales contract carefully. For any question about their rights or possible financial consequences, a notary or a specialised lawyer can help.

What this means for Cannes and the Côte d'Azur

What this means in Cannes and on the Côte d'Azur: this Nice case is a reminder that off-plan purchases carry risks, particularly when a construction site stops for technical or legal reasons. For a buyer or investor in the region, it is worth checking completion guarantees, the developer's financial strength and the delivery-deadline clauses before signing. For an owner or landlord, the key is also to understand the consequences of a delayed handover. As every situation is particular, a notary or lawyer can provide personalised advice.

Article written by agwelcome with the help of artificial intelligence, based on the article from Nice-Matin cited at the top of the page. It does not replace the advice of a notary, a lawyer or any other professional. Topics: Côte d'Azur, Rentals.

A question about your property?

Sales, rentals, estates, valuations: write to me on WhatsApp, I will reply promptly.

Write on WhatsApp
How do you prefer to contact me? Phone call+33 6 26 94 65 13 Send a text message+33 6 26 94 65 13 I reply straight away, within a few minutes.